A MODEL OF THE 4BEDROOM CONSTRUCTION

01. EXCAVATION OF TRENCH

01A. MOUNTING THE REINFORCEMENT

02 BLINDING OF TRENCH

03. LAYING OF FOUNDATION BLOCKS

05 LAYING OF FOUNDATION BLOCKS

06. FOUNDATION BLOCK WORK

07. LAYING OF PLUMBING PIPE AT THE DPC.

08 PLACING  OF HARDCORE FOR THE GERMAN FLOOR(DPC).

09. CASTING OF THE DPC.

10. BLOCKWORKFOR THE SUPERSTRUCTURE

11. CONSTRUCTION OF THE CONCRETE FASCIA