A MODEL OF THE 4BEDROOM CONSTRUCTION |
01. EXCAVATION OF TRENCH |
01A. MOUNTING THE REINFORCEMENT |
02 BLINDING OF TRENCH |
03. LAYING OF FOUNDATION BLOCKS |
05 LAYING OF FOUNDATION BLOCKS |
06. FOUNDATION BLOCK WORK |
07. LAYING OF PLUMBING PIPE AT THE DPC. |
08 PLACING OF HARDCORE FOR THE GERMAN FLOOR(DPC). |
09. CASTING OF THE DPC. |
10. BLOCKWORKFOR THE SUPERSTRUCTURE |
11. CONSTRUCTION OF THE CONCRETE FASCIA |